WORK TO BE COMPLETED BY AK ELECTRICS ON 2025-05-01 UNLESS STATED OTHERWISE
01. Pendant Light in Master Bedroom

02. Light in airing cupboard - NOT WITH ANDY ON 2025-05-01 - TO BE FITTED NEXT WEEK IF HE CAN NOT GET TODAY

03. Plug socket in Bertie's bedroom

04. 3 Recessed lights - downstairs hallway - NOT DELIVERED BY 2025-05-01 TO BE FITTED NEXT WEEK

05. Pendant in Front Living Room

06. 4 Double recessed lights - kitchen diner

07. 2 Double recessed lights - kitchen diner - either side of roof lantern

08. 5 Recessed lights - kitchen diner - NOT DELIVERED BY 2025-05-01 TO BE FITTED NEXT WEEK

09. 3 spotlights - one side of roof lantern - kitchen diner

10. 3 spotlights - other side of roof lantern - kitchen diner

11. Fridge needs wiring into plate so can sit back all the way

12. Not sure what to do with these whilst do not have splashback in place - please hide?

13. RJ45 connector needed on Wifi extender cable

14. 2 Spotlights in Sebbie's room

15. Garage lighting

216. External Plug socket needed for pond here

17. 1 of 3 external lights on lefthand side of building (looking at from garden)

18. Remaining 2 of 3 external lights on lefthand side of building (looking at from garden)

19. 2 External lights and 1 PIR? At back of house

20. Is this also for external power socket - on right hand side at back of house? UPDATE ANDY 2025-05-01- FOR FUTURE GARDEN LIGHTS -
NOT CONNECTED - ANDY WILL TAPE UP AND WILL BE ADDRESSED LATER

21. Cover needs putting over external extractor vent

22. 2 external lights at front of house

23. Light switch by sliding doors needs completing

24. Light switch by double door needs completing

25. Double plug socket in garage (if 2 external power sockets either side of building no need to use this for that)

26. LOFT - NEEDS ANOTHER LIGHT, POWER SOCKET/S AND ALSO RJ45 ON WIFI EXTENDER - UPDATE ANDY 2025-05-01 NO PROVISION HAS BEEN MADE FOR LIGHT OR
SOCKET - AGREED TO FIT CONNECTOR ON ETHERNET CABLE
27. NEED CERT
28. NEED LIGHT SWITCHES EXPLAINING (AND BUILDING REGS NEAR WATER ETC)
29. 2 x DOUBLE SOCKETS IN UTILITY - ADDED 2025-05-01 - BUT CAN BE FITTED IN TIME IT WOULD HAVE TAKEN TO FIT THE 8 X SMALL SPOTS


30. ISSUE WITH LIGHTS IN BOYS ROOM AND ONE LIGHT IN BATHROOM BETWEEN THE TWO - TO BE EXAMINED - SUSPECT SWITCH FOR BOYS ROOM AND BULB FOR BATHROOM
30. WORST CASE SCENARIO - FINAL LIGHTS WILL BE DONE (8 SPOTS AND WARMING CUPBOARD) W/C -2025-05-12, I WILL PAY AND THEN RECEIVE THE CERT